By law, a council has 8 weeks to decide a householder planning application, such as an extension, once it has accepted the application as valid.
Most councils in Greater Manchester do not achieve that target. For example, in the 2025 to 2026 period, the share of smaller applications that were decided in 8 weeks ranged from 72% in Bury, to 38% in Oldham.
In our experience, planning permission for most house extensions usually takes around 12 weeks after submission. However, allow for a longer time period in areas like Oldham, Salford and Wigan.
Also, a useful note on interpreting the data, be wary of official ‘on time’ figures, councils count extended deadlines as ‘in time’ decisions. This is why Greater Manchester councils can score between 89% to 99% on the ‘in time’ metric even when their actual figures for getting a decision within the legal deadline is actually much lower.
Greater Manchester council by council breakdown
The table below uses the government’s own figures for the 12 months to June 2026. Councils are ranked by the share of decisions they made within the 8-week legal deadline.
These figures cover all smaller (“non-major”) applications, not just house extensions. Householder applications make up between about half of them (Manchester) and four-fifths (Stockport), so they’re a good guide to set your expectations
| Council | Decided within 8 weeks | Deadline extended | Official “in time” | Within 8 weeks, a year earlier |
| England average | 53% | 41% | 91% | 55% |
| Bury | 72% | 28% | 99.6% | 68% |
| Stockport | 68% | 31% | 98% | 71% |
| Tameside | 63% | 36% | 97% | 62% |
| Manchester | 61% | 36% | 92% | 77% |
| Trafford | 60% | 36% | 92% | 71% |
| Bolton | 50% | 43% | 89% | 46% |
| Rochdale | 46% | 49% | 91% | 43% |
| Wigan | 44% | 53% | 93% | 35% |
| Salford | 41% | 55% | 94% | 48% |
| Oldham | 38% | 59% | 95% | 41% |
.
There are also some other useful points which come out of the government’s planning statistics and the Planning Inspectorate’s statistics.
- Stockport granted 95% of all applications, the highest share in Greater Manchester and Bolton granted the lowest share of applications (around 79%). Bear in mind that this data is for all applications, unfortunately we don’t have data on just house extensions.
- Across England, 91% of householder applications (these include extensions, loft conversations, and conservatories) were granted.
- Speed and approval rate do not always go together. Oldham is the slowest council in Greater Manchester but it also granted 93% of applications. On the other hand, Bury is the fastest council, but it only granted 86%.
Why is there a difference between ‘on time’ statistic and the legal 8 weeks
This is quite straightforward, when a council cannot decide an application within 8 weeks, they’ll reach out to your or your architect asking you to agree to later deadline. This is the key figure that councils are judged on, a council risks being designated as underperforming if fewer than 70% of its decisions are made within 8 weeks or an agreed extension.
It’s usually best to agree with an extension of time. You don’t have to, but if you refuse the council may decide to refuse the application rather than miss the deadline. Alternatively, you can appeal to the Planning Inspectorate for ‘non-determination’ but that might mean an 18 week wait.
What happens during those planning application process
The first step will be for the local authority to confirm that the application is valid, and then pass the case to a case officer. Your application will then go through these stages:
- Consultation. The council writes to your neighbours or puts up a site notice. People have 21 days to comment. Depending on the site, the council may ask its highways, trees, conservation or drainage teams for their views.
- Site visit. The officer usually visits, or looks at photos, to determine how the extension will affect the street and the neighbours.
- Amendments. If the officer has concerns, they may ask for amended drawings, such as a shorter depth, a lower roof or a moved window. Bigger changes can mean consulting the neighbours again.
- Decision.
Objections from neighbours don’t mean an automatic refusal. The council can only weigh planning issues, such as loss of light, privacy or how the extension looks.
Permitted development
Permitted development is a really important thing to understand when looking at building a house extension, and I recommend reading our guide to permitted development rights, and, for conservatories, whether conservatories fall under permitted development.
In short, permitted development rights let you build some extensions without applying for planning permission, as long as you stay within set limits on size, height and position. There’s no application process but you have to comply with all of the conditions.
Prior approval for larger single-storey extensions
If you want a single-storey rear extension up to 6 metres deep (8 metres for a detached house), you can use the prior approval route. The council consults your neighbours and has 42 days to decide. See our guide on prior approval [link]
Lawful Development Certificates
If you’re building under permitted development, you don’t need to apply for anything.
However, a Lawful Development Certificate [link] gives you written proof that the proposed house extension is allowed. This is primarily useful if you’re in a conservation area or have other reasons to think that your permitted development rights do not apply.
Whichever route you take, you’ll still need Building Regulations approval.
How to keep your application moving
You can’t control how busy your council is, but you can avoid most of the delays that come from your side:
- Get the application right first time.
- Design with the council’s guidance in mind.
- Talk to your neighbours before you apply..
- Reply quickly.
- Track your application.
Talk to us about your extension
We build extensions across Greater Manchester, so we see how long planning takes in each borough. If your extension needs planning permission, we’ll work with your own architect or with our partner architects. We’ll plan the build around the planning timetable, so the Building Regulations side is ready once permission comes through.
If you’re not sure whether you need planning permission at all, or how long it’s likely to take where you live, get in touch with Allgood Construction. We’ll talk it through with you and give you a no-obligation quote.